ABSTRACT
El Guavio Hydroelectric Plant (1,260 MW), operated by Enel Colombia, faces an accelerated sedimentation process threatening the operability of its deep water intake, located approximately 135 m below the reservoir’s mean level. Given the impossibility of constructing a new permanent intake in the short term, SKAVA Deep Solutions designed, fabricated and installed an innovative temporary solution: a perimetral protection screen composed of 24 prefabricated steel sheet-pile modules, installed entirely through saturation diving at great depth, in zero-visibility conditions and with ROV assistance.
The intervention increased the effective operational height of the intake structure by 7.8 m, extending the service life of the intake by approximately four additional years. The project was completed within the scheduled plant shutdown, with no disabling incidents and no environmental impact, establishing a milestone in high-altitude underwater engineering in Latin America.
Keywords: deep water intake, sedimentation, sheet piles, saturation diving, temporary rehabilitation, Guavio.
1. INTRODUCTION
Deep water intakes in hydroelectric plants constitute strategically critical infrastructure whose operation may be compromised by sedimentation processes that exceed original design projections. In the context of increasing climate variability, rates of solid material accumulation in high-altitude reservoirs tend to accelerate, prematurely reducing the service life of intake systems and increasing the risk of particulate matter entering the turbine train.
El Guavio Hydroelectric Plant, one of Colombia鈥檚 most powerful facilities with 1,260 MW of installed capacity, faces precisely this scenario. Its original intake was designed to withstand approximately 35 years of sediment accumulation; however, adverse climatic factors caused sedimentation rates significantly higher than projected, reducing the structure鈥檚 operational horizon.
Given the impossibility of constructing a permanent intake in an alternative location in the short term, an interim plan was activated with the objective of extending the operation of the existing intake for approximately four additional years. This paper describes the underwater engineering solution developed by SKAVA Deep Solutions, a company specializing in deep-water operations, which led the design, fabrication and installation of a perimetral protection screen under extreme conditions.
2. CONTEXT AND PROBLEM STATEMENT
2.1 Infrastructure Description
The deep water intake of Guavio Plant operates at approximately 135 m below the reservoir鈥檚 mean water level. The structure consists of concrete edges supporting a metallic grating cage that allows water flow to enter the pressurized conveyance system.
The original design provided for a service life of approximately 35 years against progressive sediment accumulation. The hydrostatic pressure at this depth exceeds 13.5 kg/cm虏, imposing severe constraints on both materials and intervention procedures.
2.2 Sediment Accumulation: The Critical Threat
The primary operational risk in high-altitude reservoirs lies in the progressive increase of sediment levels. Due to natural hydrodynamic processes and upstream erosion, the reservoir floor experiences a constant accumulation of solid material (sands, gravels and silts). This accumulation posed a critical threat of reaching the elevation of the intake tower鈥檚 suction screen, with potentially catastrophic consequences:
鈼� 听 听 听 Erosive damage to turbine blades: the abrasive material would act as an accelerated wear agent, drastically reducing equipment efficiency and service life.
鈼� 听 听 听 Obstruction of auxiliary systems: clogging of cooling ducts and control circuits.
鈼� 听 听 听 Instability of the national power supply: unscheduled shutdowns for emergency repairs would compromise the stability of the interconnected grid, with large-scale economic and social impact.
3. GENERAL CONCEPT
The objective of the interim plan was to allow additional sediment accumulation against the intake walls without allowing it to enter the turbine flow. To achieve this, the approach proposed blocking water passage through the vertical faces of the intake cage, allowing flow only through the top face.
In this way, the effective permissible sedimentation height was increased, temporarily extending operations while a permanent solution was developed elsewhere in the facility. The heightening structure had to be structurally robust against the hydrodynamic suction forces generated during full-load operation, and its installation had to be feasible at 130 m depth under near-zero visibility conditions.
4. OPTIMIZED DESIGN DEVELOPMENT
4.1 Propuesta Inicial del Client
Enel provided a basic engineering-level solution based on steel plates bolted directly to the existing screen. This alternative presented critical limitations that compromised both its constructability and its effectiveness:
鈼� 听 听 听 No sealing solution between the plates and the concrete.
鈼� 听 听 听 Incomplete sizing of fastening bolts.
鈼� 听 听 听 Undefined overlaps at structural corners.
鈼� 听 听 听 Lack of guaranteed watertightness.
鈼� 听 听 听 High degree of direct human intervention, not feasible at 130 m depth under zero-visibility conditions.
4.2 SKAVA’s Proposed Solution: Sheet-Pile Modules
SKAVA鈥檚 first task was to review the constructability of the basic design and propose an alternative that would guarantee watertightness and ease of installation, reducing human exposure to the absolute minimum.
After evaluating multiple alternatives, a solution based on prefabricated high-strength steel sheet-pile modules was adopted. A total of 24 modules were designed, manufactured entirely in steel and protected with anti-corrosion coating systems certified for long-term submerged environments.
The interlocking system inherent to the sheet piles enabled sequential module engagement, achieving a complete seal around the intake perimeter. The core elements of the optimized design were:
鈼� 听 听 听 Prefabricated and stiffened modules: welded with stiffening beams, fully assembled and dimensionally validated in the workshop prior to transport.
鈼� 听 听 听 Specialized bottom seal: each module incorporated a perimetral bottom seal to ensure waterproofing at the interface with the concrete structure.
鈼� 听 听 听 Bolted shear connections: designed to ensure structural load transfer between adjacent modules and resist suction forces during full-load operation.
鈼� 听 听 听 Blind-assembly design: male-female interfaces and high-security bolts enabling precise fit without direct visual contact.
For model validation, advanced computational fluid dynamics analyses were conducted to ensure the structure could withstand not only static hydrostatic pressure exceeding 13 kg/cm虏, but also the dynamic suction forces generated when the plant operates at full load (1,260 MW).
5. DEPLOYMENT LOGISTICS
The mobilization of resources for this project entailed a continental-scale logistics operation. The saturation diving system was transported from Mexico in a multimodal operation (maritime and overland) under strict international industrial safety standards.
Once in Colombian territory, more than 1,000 metric tons of equipment crossed the complex Andean road network. A fleet of 89 trucks transported everything from heavy steel structures to delicate hyperbaric life-support systems. Breathing gas management represented another major challenge: at 130 m depth, atmospheric air becomes toxic, requiring the preparation and transport of 4,500 m鲁 of helium and 1,000 m鲁 of oxygen for the formulation of the Heliox mixture used in saturation operations.
Construction operations were organized into three simultaneous work fronts:
鈼� 听 听 听 External logistics front: support operations in Bogot谩, Cartagena de Indias, the reservoir shoreline, and other staging and coordination points.
鈼� 听 听 听 Main floating platform: a modular structure of 18 interconnected flexiboats, covering approximately 700 m虏, anchored at four points directly above the intake. It housed the 100-ton main crane, the ROV control station, and the saturation module “El Dorado”.
鈼� 听 听 听 Direct underwater front: execution of works at the intake using saturation divers at 130 m depth.
6. OPERATIONAL EXECUTION: INSTALLATION UNDER EXTREME CONDITIONS
6.1 Saturation Diving
The most critical activity of the project was carried out using saturation diving technology. This procedure allows the divers鈥� bodies to equilibrate with the gas pressure at the working depth, eliminating the need for daily decompressions and enabling extended periods of effective bottom work.
The divers remained under saturation throughout the approximately 30-day campaign inside the “El Dorado” module, descending via a diving bell. Each dive deployed two divers, though only one performed active work. Operations were organized in 8-hour shifts with a rotating team of six divers, ensuring uninterrupted operational continuity.
6.2 Assembly Under Zero-Visibility Conditions
At 130 meters depth and in zero-visibility conditions, a diving team successfully performed a tactical assembly working entirely by touch. Mission success depended on an advanced technological network that included:
– 听 听 听Continuous communication: linking the surface supervisor, the diving bell, and the diver.
– 听 听 听Digital visualization: high-resolution sonar systems monitoring the area in real time.
– 听 听 听Robotic assistance: an ROV was used to position and deliver each module with exact precision prior to final manual adjustment.
6.3 Lifting Engineering and Millimetric Positioning
The lowering of the heavy modules was carried out using high-capacity cranes integrated into the floating platform. Rigorous Lifting Plans were implemented, accounting for submarine current dynamics and the effect of pressure on component stability.
Synchronization between the surface operator and the underwater team enabled control of the “pendulum effect” of loads at depth, allowing each component to engage precisely with its structural guides. This procedure was repeated systematically until all 24 modules were installed, after which the bolted shear connections were fitted and the assembly was verified through a final ROV survey.
6.4 Safety Management and Operational Continuity
Operations were sustained continuously for more than 30 days. Logistical support was reinforced by a fleet of support vessels managing the constant flow of supplies, personnel and materials. The physical well-being of the divers was overseen by a specialized medical team and life-support technicians, who provided uninterrupted supervision of saturation chamber conditions, managing gas mixtures and decompression procedures in accordance with international standards.
The project was executed by 140 specialized professionals from Chile, Colombia, Brazil and Mexico. The technical expertise of the team, complemented by constant on-site supervision, enabled the completion of operations with zero disabling incidents and no environmental impact on the reservoir ecosystem.
7. RESULTS ACHIEVED
The implemented temporary solution delivered the following quantifiable results:
鈼� 听 听 听 A 7.8 m increase in the operational height of the intake structure, enabling greater sediment accumulation without entry into the turbine flow.
鈼� 听 听 听 Extension of the intake鈥檚 service life by approximately three additional years, providing the time margin required for the development of the permanent intake solution.
鈼� 听 听 听 Execution completed within the scheduled plant shutdown, confirming the constructability of the methodology under extreme conditions.
鈼� 听 听 听 Zero disabling accidents and zero environmental impacts recorded throughout the entire campaign.
8. LESSONS LEARNED
The execution of the temporary heightening at Guavio yielded high-value lessons for future interventions in deep hydraulic infrastructure:
鈼� 听 听 听 Constructability as the primary design criterion: in works at great depths and under zero-visibility conditions, success depends on engineering conceived from the earliest stages with assembly constraints, logistics and minimization of human exposure in mind.
鈼� 听 听 听 Modular approach to risk minimization: the prefabricated modular design significantly reduced the need for direct human intervention, requiring only one active diver per installation operation.
鈼� 听 听 听 ROV-diver integration as a standard methodology: the combination of remotely operated vehicles for positioning and geometric control with saturation divers for fitting and fastening maneuvers proved decisive for the precision and safety of the installation.
鈼� 听 听 听 Pre-installation workshop validation: the complete pre-assembly of all modules before transport to site prevented dimensional interferences during underwater installation, saving critical dive time.
鈼� 听 听 听 Gas management in high-altitude logistics: advance planning of Heliox mixture supply at industrial-scale volumes is essential to ensure operational continuity in projects of this magnitude.
9. CONCLUSIONS
The temporary heightening of the deep water intake at El Guavio Hydroelectric Plant constitutes a singular case in Latin American underwater engineering. SKAVA demonstrated that it is possible to design, fabricate and install highly complex structures at extreme depths, under zero-visibility conditions and to world-class safety standards.
The solution based on prefabricated sheet-pile modules, optimized for remote installation with minimal direct human intervention, overcame the limitations of the original basic design and delivered a structure with validated hydraulic, structural and watertightness performance. The effective integration of saturation diving and ROV as complementary tools made the decisive difference in the feasibility and safety of execution.
Beyond the immediate result, this project provides a replicable methodological model for the temporary rehabilitation of hydraulic infrastructure affected by accelerated sedimentation in deep-water contexts, contributing to the energy resilience of large-scale hydroelectric systems across Latin America and the world.